Tuesday, March 26, 2013

Bunker Update...

  • Green-side bunkers on number 9 were finished the week of March 22nd.  
  • Green-side bunker on number 7 will be completed by March 29th.
  • Green-side bunkers on number 1 and 2 will be sprayed with Klingstone (bunker liner) on March 28th and will be completed by April 5th.

Santiago coring out the bunker sand.  Santiago works at Granite Bay CC and we were fortunate to have him excavating the bunkers.


Viliulfo is spraying the Klingstone bunker liner while Ildefonso, Rick and Eric apply a light coat of sand.

The sod goes down by Rick, Eric and Seth.  Jose and Saul add our new bunker sand and rake smooth.

The finished product.